Math Problem Statement
Q 5 - A contract was to be completed in 56 days and 104 men were set to works, Each working 8 hours per days. After 30 days , 2/5 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
Solution
Let's solve the problem step-by-step.
Step 1: Calculate Total Work in Man-Hours
The total work is to be completed in 56 days by 104 men, each working 8 hours per day.
Total work (in man-hours) can be calculated as:
Let's compute this:
Step 2: Calculate Work Completed in 30 Days
It is given that after 30 days, of the work is completed.
Work completed in 30 days:
Step 3: Calculate Remaining Work
Remaining work to be done:
Step 4: Calculate Remaining Days and Hours per Day
The work must be completed in 56 days. Since 30 days have already passed, the remaining days are:
Now, each man is working 9 hours per day instead of 8 hours.
Step 5: Calculate Total Number of Man-Hours Required Per Day
Let be the number of additional men required.
The total number of men working now will be:
Total number of man-hours required per day to complete the remaining work:
Step 6: Set up the Equation for Remaining Work
The total man-hours required to complete the remaining work in 26 days is:
Simplify this equation to find :
Since the number of men cannot be a fraction, we round up to the nearest whole number:
Conclusion
16 additional men should be employed to complete the work on time.
Would you like more details or have any questions?
Related Questions:
- How would the solution change if the initial number of men was different?
- What happens if the number of working hours per day is increased further?
- How much work would each man need to do if no additional workers were hired?
- What if the work completed in the first 30 days was more than ?
- How would the calculations change if the total duration was less than 56 days?
Tip: Always consider the impact of changes in work hours or number of workers on the overall timeline for project completion.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time
Proportions
Equations
Formulas
Total Work = Number of Men × Number of Days × Number of Hours per Day
Remaining Work = Total Work - Work Completed
Man-hours per Day = (Number of Men) × (Hours per Day)
Equation to Find Additional Men: (Total Men) × Hours per Day × Remaining Days = Remaining Work
Theorems
Proportionality Theorem in Work Problems
Suitable Grade Level
Grades 9-12
Related Recommendation
Work and Time Problem: Calculating Additional Workers Needed for Project
How to Calculate the Number of Additional Workers Needed to Complete a Road Project on Time
Calculating Additional Workers for a Building Project with Delays
Find Minimum Additional Workers for School Construction Project
Calculate Additional Workers Needed to Complete a Job on Time