Math Problem Statement
Solution
The problem in the image provides the following details:
- A school construction project is expected to be completed in 42 days with 60 workers.
- On the 21st day, 17 workers become sick and 3 workers have minor injuries, and they only return to work after 2 days.
- The goal is to find how many additional workers are needed to ensure the project finishes on time.
Solution Approach:
-
Initial Workload Calculation:
- Total work =
- This means the project requires 2520 worker-days to be completed on time.
-
Work Done in the First 20 Days:
- In the first 20 days, 60 workers work every day:
- So, after 20 days, 1200 worker-days have been completed, leaving:
-
Work on Day 21 and Day 22 (with reduced workers):
- On the 21st and 22nd days, only are working.
- Work done in these 2 days:
- After these two days, the remaining work is:
-
Work After Day 23 (normal workers back):
- From day 23, all 60 workers return.
- Time remaining = .
- Work capacity with 60 workers for the remaining 20 days is:
- This is 40 worker-days short ().
-
Finding the Additional Workers:
- To cover the remaining 40 worker-days over 20 days, we need:
- Therefore, 2 additional workers are needed.
Answer:
The minimal number of additional workers needed is 2.
Would you like more details or have any questions?
Here are 5 related questions:
- How would the solution change if the 17 workers only returned after 3 days instead of 2?
- What would happen if the workers’ productivity was not uniform?
- How would the calculations change if only 50 workers were available from the start?
- What if the 3 workers who were injured never returned? How many more workers would be needed?
- Could overtime or longer working hours reduce the need for additional workers?
Tip: Breaking down complex problems into smaller time frames or stages can simplify your calculations!
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work rate
Algebra
Proportions
Formulas
Total Work = Number of workers * Time (days)
Work rate = Work done per day
Additional workers needed = (Remaining work / Remaining time)
Theorems
Work-Time Proportionality
Suitable Grade Level
Grades 10-12
Related Recommendation
Work Problem: Finding Additional Workers to Complete a Project on Time
How to Calculate the Number of Additional Workers Needed to Complete a Road Project on Time
Calculating Additional Workers for a Building Project with Delays
Workforce Calculation for Construction Project Deadline
Work and Time Problem: Calculating Additional Workers Needed for Project