Math Problem Statement
A contractor engages 54 workers to complete a job in 21 days after working for 3 days he found that the he would get the work completed in 28 days if he does not incres a number of workers how many more workers should he engage to get the work done in timeif he does not incres a number of workers how many more workers should he engage to get the work done in time
Solution
Problem Breakdown:
- The contractor initially engaged 54 workers to complete a job in 21 days.
- After working for 3 days, the contractor realizes that if he continues with the same number of workers, the job will take 28 days to complete.
- The task is to find out how many additional workers are needed to complete the job in the original 21 days timeframe.
Step-by-Step Solution:
-
Determine the total amount of work:
Total work can be expressed in terms of worker-days (number of workers × number of days).
Initially, the contractor planned to complete the job with 54 workers in 21 days. So, the total amount of work (W) is:
-
Calculate the work done in the first 3 days:
In the first 3 days, the contractor worked with 54 workers. Therefore, the amount of work completed in these 3 days is:
-
Calculate the remaining work:
The remaining work after 3 days is the total work minus the work completed in these 3 days:
-
Determine the new rate of work to finish in 28 days:
The contractor realizes that with the same 54 workers, the remaining work would take 28 days in total. So, the number of worker-days needed for the remaining work if 54 workers are employed for 28 days: However, the remaining work is only 972 worker-days, so this is why the timeline increases to 28 days.
-
Calculate how many workers are needed to finish in the original 21 days:
The contractor wants to complete the job in the original 21 days. After 3 days of work, there are 18 days left. Let the number of workers needed to complete the remaining work in 18 days be x.
The total work remaining (972 worker-days) should now be completed by these x workers in 18 days: Equating this to the remaining work: Solving for x:
So, the contractor needs 54 workers to complete the remaining work in 18 days.
-
How many more workers to engage?
The contractor already has 54 workers. Therefore, the number of additional workers needed is:
Therefore, no additional workers are needed to complete the job in the remaining time.
Conclusion:
No additional workers are needed. The current workforce of 54 workers can complete the job in 21 days.
Do you have any questions, or would you like more details on a particular part of the solution?
Here are 5 additional questions to expand on this:
- How would the solution change if the contractor had less than 54 workers initially?
- What if the contractor wanted to finish the job in fewer than 21 days?
- How do worker efficiency and productivity affect these types of problems?
- Can you determine the amount of work done per day by each worker?
- How would delays in the work affect the number of workers needed?
Tip: In time-based work problems, keeping track of the amount of work done per day is key to solving efficiently.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time
Proportions
Formulas
Work = Number of Workers × Number of Days
Remaining Work = Total Work - Work Completed
Workers Needed = Remaining Work / Remaining Days
Theorems
-
Suitable Grade Level
Grades 9-10
Related Recommendation
Workforce Calculation for Construction Project Deadline
Work Problem: Finding Additional Workers to Complete a Project on Time
Calculate the Number of Builders Required to Finish a Building in 20 Days
How Many Workers are Required to Complete a Job in 18 Days?
Solve Work and Time Problem with Additional Workers