Math Problem Statement
A contractor agrees to aly a road of 3000 long in 30 days. He employs 50 men who work for 8 hours a day. After 20 working days, he fins that only 1200m of the road is completed. How many more men should he employ to finish the work on time if each man now works 10 hours a day.
Solution
Let's break down the problem step by step:
Given:
- Total road length = 3000 meters
- Total time to complete = 30 days
- Total men employed = 50 men
- Working hours per day initially = 8 hours
- After 20 days, only 1200 meters have been completed.
- Now, each man works 10 hours a day.
We need to determine how many additional men the contractor needs to hire to finish the road in the remaining time.
Step 1: Calculate the total work required to complete the road.
The total work needed is the remaining distance:
Step 2: Determine the total work already done by the current workers in the first 20 days.
The number of men working in the first 20 days is 50, and they work 8 hours per day. The total number of man-hours spent in the first 20 days is:
Now, since 1200 meters of road have been completed in 8000 man-hours, the number of man-hours required to complete 1 meter of road is:
Step 3: Calculate how many man-hours are required to complete the remaining 1800 meters of road.
To finish the remaining 1800 meters, the total number of man-hours required is:
Step 4: Calculate the remaining number of days.
Since 20 days have already passed, there are 10 days left to finish the remaining work.
Step 5: Determine how many man-hours can be completed in the remaining time.
If each man now works 10 hours per day, the total number of man-hours that can be worked by the existing 50 men in the next 10 days is:
Step 6: Calculate the shortfall in man-hours.
The total number of man-hours required to complete the remaining work is 12,000 man-hours, and the current team can only contribute 5000 man-hours. Therefore, the shortfall in man-hours is:
Step 7: Calculate the number of additional men needed.
If each new man works 10 hours per day for the remaining 10 days, each man will contribute:
Now, to cover the shortfall of 7000 man-hours, the number of additional men required is:
Conclusion:
The contractor needs to employ 70 additional men to finish the work on time.
Let me know if you have further questions or need clarification!
Related Questions:
- How can we calculate the number of man-hours required for different types of work?
- What is the impact of changing work hours on project timelines?
- How does increasing the number of workers affect the overall efficiency of a project?
- How do you calculate the efficiency of a team based on their output?
- What other factors might influence the contractor’s decision to hire more workers?
Tip:
When facing tight project deadlines, it's crucial to carefully assess both the number of workers and the amount of time remaining to ensure you can meet the goal on time.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time
Man-Hours
Proportions
Formulas
Man-hours = Number of men × Hours per day × Number of days
Man-hours per meter = Total man-hours / Distance completed
Number of additional men = Shortfall in man-hours / (Hours per day × Number of days per man)
Theorems
-
Suitable Grade Level
Grades 8-10
Related Recommendation
Work Problem: Finding Additional Workers to Complete a Project on Time
Solve Work and Time Problem with Additional Workers
Work and Time: Contractor Problem on Road Construction and Worker Adjustment
Find Minimum Additional Workers for School Construction Project
How to Calculate Man-hours for Work Schedules: Construction Example