Math Problem Statement
A is 20% more efficient than B and takes 40 days less than what B takes to complete a particular job. B is 50% more efficient than C. On the same job, A works for 50 days and quits. And then B takes over and works for 20 days and quits. C completed the remaining work. Find the number of days taken by C to complete the work.
Solution
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time Problems
Efficiency
Algebra
Formulas
Work done = Efficiency × Time
Efficiency relationship between A and B: r_A = 1.2 × r_B
Efficiency relationship between B and C: r_B = 1.5 × r_C
Remaining work = Total work - Work done by A and B
Theorems
Proportionality between time, work, and efficiency
Work formula: Total work = Efficiency × Time
Suitable Grade Level
Grades 9-11
Related Recommendation
Calculate Days for A, B, and C to Complete 84% of the Work
Work Efficiency Problem with Three Workers Solving Collaborative Tasks
Work and Efficiency Problem Solving: A, B, and C Completing a Task Together
Work and Time Problem: A, B, and C Working Together
Calculate Completion Time for Work with A, B, and C