Math Problem Statement
A is 20% more efficient than B and takes 40 days less than what B takes to complete a particular job. B is 50% more efficient than C. On the same job, A works for 50 days and quits. And then B takes over and works for 20 days and quits. C completed the remaining work. Find the number of days taken by C to complete the work.
Solution
Let the amount of work required to complete the job be represented as .
Step 1: Defining efficiency and time for A, B, and C
Efficiency of B:
Let B's rate of work (efficiency) be units of work per day. Thus, B takes days to complete the job.
Efficiency of A:
A is 20% more efficient than B, meaning A's rate of work is .
Let the time taken by B to complete the job be days. From the problem, we know that A takes 40 days less than B to complete the job: Since the time to complete the job is the total work divided by the rate of work, we know: Thus, from the given information, we have: Multiplying through by to eliminate the denominators: Thus, B's rate of work is .
Efficiency of C:
B is 50% more efficient than C, meaning B’s rate of work is 1.5 times that of C. Hence, C's rate of work is:
Step 2: Amount of work completed by A, B, and C
Work done by A in 50 days:
A works for 50 days, so the work done by A is: Thus, A completes of the total work.
Work done by B in 20 days:
B works for 20 days, so the work done by B is: Thus, B completes of the total work.
Remaining work for C:
The total work done by A and B is: Thus, the remaining work for C is:
Step 3: Time taken by C to complete the remaining work
The time taken by C to complete of the total work is:
Final Answer:
C takes 240 days to complete the remaining work.
Let me know if you'd like more details or have any questions.
Here are 5 related questions for further practice:
- If A worked for 40 days instead of 50, how many days would C take to complete the remaining work?
- If C were 25% more efficient, how many days would C take to complete the work left after A and B?
- How long would it take A to complete the entire job on their own?
- If B worked for 30 days instead of 20, how much work would be left for C to complete?
- If C worked for the first 60 days, how much work would be left for A and B to complete?
Tip: Efficiency comparisons are often relative, so always express one worker's efficiency in terms of another to simplify the calculations.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time Problems
Efficiency
Algebra
Formulas
Work done = Efficiency × Time
Efficiency relationship between A and B: r_A = 1.2 × r_B
Efficiency relationship between B and C: r_B = 1.5 × r_C
Remaining work = Total work - Work done by A and B
Theorems
Proportionality between time, work, and efficiency
Work formula: Total work = Efficiency × Time
Suitable Grade Level
Grades 9-11
Related Recommendation
Calculate Days for A, B, and C to Complete 84% of the Work
Work Efficiency Problem with Three Workers Solving Collaborative Tasks
Work and Efficiency Problem Solving: A, B, and C Completing a Task Together
Work Problem: B and C start, then A finishes the remaining work
Work and Time Problem: A, B, and C Working Together