Math Problem Statement

  1. Using your spreadsheet, estimate how long (in years) it should have taken Tesla to build 474,000 cars for the reserve list of customers.

Note: Round your answer to 1 decimal place.

one 8 hour shift ......... cars her hour two 8 hour shift ......... cars per hour

Solution

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Rate of Production
Proportions
Division

Formulas

Time = Total Cars / (Cars per Hour × Hours per Shift × Shifts per Day × Days per Year)