- Twenty-eight persons can do a job in 60 days. They all start complete. Five persons quit the job at the beginning of the 16th day. They were reinforced with 10 persons at the beginning of the 45th day. How many days was the job delayed? A. 5.78 days C. 1.97 days B. 1.14 days D. 2.45 days