Math Problem Statement
A and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after, 2 more days. B alone could do the work in how many days ?
Solution
Let's solve this step by step.
Step 1: Determine the combined work rate of A and B.
A and B together can complete the work in 3 days. Therefore, their combined work rate is:
Step 2: Calculate the work done by A and B in 2 days.
Since A and B work together for 2 days, the amount of work completed in these 2 days is:
Step 3: Determine the remaining work.
After 2 days, of the work is completed. Therefore, the remaining work is:
Step 4: Determine the work rate of A alone.
Let's assume A can complete the work in days. Therefore, A's work rate is:
Step 5: Calculate the time taken by A to complete the remaining work.
The remaining of the work is completed by A in 2 days after B left. Therefore:
Solving for :
So, A alone can complete the entire work in 6 days.
Step 6: Determine B's work rate.
Let be the number of days B alone would take to complete the work. The combined work rate of A and B is:
Substitute into the equation:
Step 7: Solve for .
Therefore, B alone could do the work in 6 days.
Would you like more details, or do you have any questions?
Here are 5 related questions you might find interesting:
- How long would it take A alone to complete half of the work?
- If B worked alone for 2 days, how much of the work would be left?
- What if A and B started together, but B left after 1 day? How many more days would A need to complete the work?
- If both A and B work on the task, but A is twice as efficient as B, how long would they take to complete the work together?
- How would the result change if B left after only 1 day instead of 2 days?
Tip: When solving work problems, it's often helpful to express work rates as fractions of the total work per unit time (e.g., work per day) to make the calculations easier.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time
Rates
Algebra
Formulas
Work rate = 1 / Time
Combined work rate: 1/a + 1/b = 1/c
Theorems
Work-Time Theorem
Suitable Grade Level
Grades 9-11
Related Recommendation
A and B Work Together to Complete a Job: How Long Will it Take?
Work and Efficiency: Calculating Days for B to Finish a Task
Solve Work and Time Problem: A and B Completing a Task Together and Separately
Calculate Remaining Work Completion Time for A After B Leaves
Solve Work and Time Problem: B's Solo Work Time