Math Problem Statement
Shrewsbury Technologies, which manufactures high-technology instruments for spacecraft, is considering the sale of a navigational unit to a private company that wishes to launch its own communications satellite. The company plans to purchase 8 units, although it would also consider buying 16 units. Shrewsbury has started a chart relating labor time required to units produced:
Unit Produced (X) Time Required to Produce the Xth Unit 1 22,000 hours 2 15,400 hours 4 10,780 hours 8 ? 16 ?
Solution
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Learning Curve Theory
Formulas
Y = aX^b
Theorems
-
Suitable Grade Level
Advanced Level
Related Recommendation
Calculate Labor Time Using Learning Curve Formula
Understanding Labor Hour Calculation Using Learning Curve and Cumulative Improvement Factor
Learning Curve Equation: Solving for k and Days for Production Target
Estimating Labor Hours Using Learning Curves: Example and Solution
Learning Curve Calculation for Window Assembly Time with 85% Learning Rate