Math Problem Statement
Thirty men take 20 days to complete a job working 9 hours a day. How many hours a day should 40 men work to complete the job?
Solution
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Man-hours
Proportional reasoning
Formulas
Man-hours formula: Total man-hours = Number of men × Number of days × Hours per day
Theorems
-
Suitable Grade Level
High School