6 arbeiter benötigen für einen auftrag 12 tage je 8 stunden. Wie viele tage sind nötig, wenn die tagesarbeitszeit um eine stunde ansteigt und zwei zusätzlichhe arbeiter mitwirken?
Solution
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work Rate Problems
Proportions
Unit Conversion
Formulas
Total Work = Number of Workers × Number of Days × Hours per Day
New Number of Days = Total Work / (New Number of Workers × New Hours per Day)