Math Problem Statement
Solution
The problem states:
- 20 builders working 6 hours a day can finish a building in 30 days.
- We need to find out how many builders would be required to finish the building in 20 days if they worked for 10 hours a day.
Solution:
First, let's calculate the total amount of work done in builder-hours under the given scenario:
- Total work done (builder-hours) in the original case:
- 20 builders × 6 hours/day × 30 days = 3600 builder-hours.
Now, we need to determine how many builders are required to finish the same amount of work in 20 days if they work 10 hours a day:
- Total work needed in new scenario:
- Let the number of builders required be .
- The total work they will do in 20 days at 10 hours/day is .
We want this to equal the total work from the original case:
- Solving for :
Thus, 18 builders would be required to finish the building in 20 days if they work 10 hours a day.
Do you have any questions or would you like further details? Here are 5 related questions for further exploration:
- If the number of days were reduced to 15, how many builders would be needed if they still worked 10 hours a day?
- What if the builders worked 8 hours a day instead of 10, how many builders would be required?
- How would the calculation change if the productivity of each builder varied?
- If 25 builders were available, how many days would it take them to finish the building working 10 hours per day?
- What if the total hours of work required increased by 20% due to unexpected changes in the project?
Tip: When solving work-related problems, always remember to compute the total amount of work done (e.g., worker-hours) and then adjust based on the variables that change (time, number of workers, or hours worked per day).
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work Problems
Proportions
Algebra
Formulas
Total Work = Number of Workers × Hours per Day × Days
Theorems
-
Suitable Grade Level
Grades 8-10
Related Recommendation
Calculate Additional Workers Needed to Complete a Job on Time
How Many Workers are Required to Complete a Job in 18 Days?
Work Rate Problem: 9 Builders in 12 Days, Find Time for 6 Builders
Work-Rate Problem: How Many Workers Needed to Complete a Job in 18 Days
Work-Time Calculation: Determining Number of People Needed for a Project in 6 Days