Math Problem Statement
ThiX, Y and Z can complete a piece of work in 36 days, 90 days and 54 days respectively. All the three started the work together but Y left after ten days and X left the work after two more days. In how many days was the entire work completed?
Solution
To solve this problem, we need to determine how much work