Math Problem Statement
X, Y and Z can complete a piece of work in 36 days, 90 days and 54 days respectively. All the three started the work together but Y left after ten days and X left the work after two more days. In how many days was the entire work completed?
Solution
To solve this problem, we need to determine how much work each person (X, Y, and Z) completes in a day and then track their contributions over the given days.
Step 1: Calculate the Work Rates of X, Y, and Z
-
X can complete the work in 36 days.
So, X’s work rate is of the work per day. -
Y can complete the work in 90 days.
So, Y’s work rate is of the work per day. -
Z can complete the work in 54 days.
So, Z’s work rate is of the work per day.
Step 2: Calculate the Work Done by X, Y, and Z in the First 10 Days
For the first 10 days, all three (X, Y, and Z) work together.
The combined work rate for X, Y, and Z is:
To add these fractions, first find the least common denominator (LCD), which is 540.
Adding these:
This is the amount of work done per day by all three together.
So, the work done in the first 10 days is:
Step 3: Calculate the Work Done After Y Leaves
After 10 days, Y leaves the work. Now, only X and Z continue working together.
Their combined work rate is:
The LCD for 36 and 54 is 108.
Adding these:
They work together for 2 days before X leaves. The work done in these 2 days is:
Step 4: Calculate the Remaining Work and Z’s Contribution
Total work done so far is:
So, the remaining work is:
Now, Z alone works to complete the remaining of the work. Z’s work rate is per day.
The time taken by Z to complete of the work is:
Step 5: Calculate the Total Time Taken
The total time taken to complete the work is:
- 10 days (when X, Y, and Z worked together)
- 2 days (when X and Z worked together)
- 18 days (when Z worked alone)
Final Answer
The entire work was completed in 30 days.
Would you like further details or have any questions?
Here are 5 related questions:
- How would the solution change if Y left after 5 days instead of 10?
- What if Z’s efficiency increased, and he could finish the work in 45 days?
- How would the work distribution change if X worked alone for the first 5 days?
- Can you derive a general formula for the time taken if workers leave at different stages?
- What if one more worker joined Z after X left?
Tip: Breaking down complex word problems into smaller steps helps prevent errors in calculations.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Rate of work
Combined work
Days to complete
Formulas
-
Theorems
-
Suitable Grade Level
High School
Related Recommendation
Calculate Completion Time for Work Problem with X, Y, and Z
Work and Time Problem: Calculating Y's Time to Complete Work Alone
Work Problem: B and C start, then A finishes the remaining work
Efficiency, Time, and Work: Solving Problems with Multiple Workers
Work Efficiency Problem with Three Workers Solving Collaborative Tasks