Math Problem Statement

Bade Midwifery's cost formula for its wages and salaries is $1,220 per month plus $246 per birth. For the month of October, the company planned for activity of 106 births, but the actual level of activity was 102 births. The actual wages and salaries for the month was $27,250. The activity variance for wages and salaries in October would be closest to:

Multiple Choice

$46 U

$984 F

$984 U

$46 F

Solution

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Cost Accounting
Variance Analysis

Formulas

Wages and Salaries = Fixed Cost + (Variable Cost per Unit × Number of Units)
Activity Variance = Planned Wages and Salaries − Wages and Salaries based on Actual Activity

Theorems

-

Suitable Grade Level

College-Level Accounting or Business