For a maintenance contract, a millwright needs to inspect 7 different generators. Each inspection takes 4 weeks. Assuming a 5-day workweek, how many workdays are required?

Solution

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Multiplication
Time Calculation
Unit Conversion

Formulas

Total workdays per generator = weeks per inspection × workdays per week
Total workdays for all generators = number of generators × workdays per generator