Math Problem Statement
Solution
Let's break down and solve the problem from the image step-by-step.
Problem Summary:
- 10 men can complete a piece of work in 12 days.
- 12 children can complete the same work in 16 days.
- 8 women can complete the same work in 20 days.
- Initially, 5 men and 10 children started working on the task.
- After 4 days, 8 children were replaced by 5 women.
We need to find in how many days the remaining work was completed after the replacement.
Step 1: Calculate the work rates of each group.
- Work rate of men: 10 men finish the work in 12 days. So, 1 man’s rate = .
- Work rate of children: 12 children finish the work in 16 days. So, 1 child’s rate = .
- Work rate of women: 8 women finish the work in 20 days. So, 1 woman’s rate = .
Step 2: Calculate the work done in the first 4 days.
- Initially, 5 men and 10 children are working.
- Work rate of 5 men = .
- Work rate of 10 children = .
- Combined work rate for the first 4 days = .
- Let's simplify:
- Work done in 4 days = .
Step 3: Remaining work after 4 days.
- Total work is 1 unit. After 4 days, of the work is done.
- Remaining work = .
Step 4: Calculate the combined rate after 4 days.
- After 4 days, 8 children are replaced by 5 women.
- New group:
- Work rate of 5 men = (same as before).
- Work rate of 2 children = .
- Work rate of 5 women = .
- Combined work rate after the replacement: Let's simplify:
Step 5: Calculate the remaining days.
- Remaining work = .
- Work rate after replacement = .
- Time to complete the remaining work = .
Final Answer:
The remaining work will be completed in 7.5 days.
The correct option is (4) 7.5.
Would you like more details or explanations on any step?
Here are 5 related questions to practice:
- If 6 men and 8 women work together, how long will they take to complete the task?
- How long would it take for 20 children alone to complete the work?
- If the number of days the work took was reduced by 2, how many additional men would be needed?
- What would happen if the replacement of children with women occurred after 6 days instead of 4?
- If only children worked from the beginning, how long would they take to finish the task?
Tip: When dealing with work problems, always convert the work rate to a "per day" basis for each group and combine them to calculate the total efficiency.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time
Efficiency
Formulas
Work rate = 1 / (people * days)
Total Work = Work rate * Time
Remaining Work = 1 - Work done
Theorems
Work formula based on group efficiency
LCM for adding work rates
Suitable Grade Level
Grades 10-12
Related Recommendation
Work and Time: Men and Women Working Together on Alternate Days
Work and Time Problem: 10 Men, 12 Women, and 18 Children Complete a Task
Calculate Work Rates: Man, Woman, and Boy Problem Solution
Solving Work and Time Problems: Calculating Task Completion Rates
Work and Time Problem: Calculate Additional Workers Required