Math Problem Statement
A man can finish a work in 12 days and a woman can finish the same work in 10 days. 2 men and 3 women work on alternate days and men start the first day. In how many days, the work will be finished?
Solution
Let the total work be represented as (a whole unit).
-
Work done by one man in one day: A man can finish the work in 12 days, so the work done by one man in one day is:
-
Work done by one woman in one day: A woman can finish the work in 10 days, so the work done by one woman in one day is:
-
Work done by 2 men in one day: Since 2 men are working on alternate days, the work done by 2 men in one day is:
-
Work done by 3 women in one day: The work done by 3 women in one day is:
-
Work done in two consecutive days: Men and women work on alternate days, with men starting on the first day. So, the total work done in two consecutive days (one day of men and one day of women) is:
To sum these fractions, we find a common denominator: Therefore, the work done in two consecutive days is of the total work.
-
Number of such 2-day cycles: To finish the entire work , let’s find how many full 2-day cycles are needed. The total work done in such cycles is: Setting this equal to 1 to find : Solving for : This means approximately full cycles are needed. Each cycle consists of 2 days, so in 2 full cycles (4 days), of the work will be completed.
-
Remaining work after 4 days: After 4 days (2 full cycles), the work done is: So, the remaining work is:
-
Final day (worked by men): On the 5th day, 2 men work. The work they complete in 1 day is: Since , the men will complete the remaining work in less than a full day.
-
Time taken on the 5th day: To calculate the fraction of the day required to finish the remaining of the work: So, the men will finish the work in of the 5th day.
Thus, the total number of days to complete the work is:
Therefore, the work will be finished in 4.4 days.
Would you like more details or have any questions? Here are 5 related questions to explore:
- How would the answer change if the woman started on the first day instead?
- What if the number of men and women working was swapped (3 men, 2 women)?
- How would you calculate the work completed if only one man and one woman worked alternately?
- Can you find a formula to generalize this problem for different work rates?
- How can you use the concept of work rates to solve problems involving machines?
Tip: When dealing with alternating workers, always calculate the work completed in one cycle before extending it to the total work.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time
Fractions
Unit Rates
Formulas
Work done by 1 man in 1 day = 1/12
Work done by 1 woman in 1 day = 1/10
Work done by 2 men in 1 day = 2 * (1/12) = 1/6
Work done by 3 women in 1 day = 3 * (1/10) = 3/10
Work done in 2 days = 1/6 + 3/10 = 7/15
Total work done in n cycles = n * (7/15)
Fraction of day required = (Remaining work)/(Work done by 2 men in 1 day)
Theorems
Concept of Work Rates
Suitable Grade Level
Grades 9-10
Related Recommendation
Calculate Work Completion with Men, Children, and Women
Work and Time Problem: How Long Will 10 Women Take to Complete the Job?
Work and Time Problem: 3 Men and 7 Women Complete Work in 10 Days
Work and Time Problem: 10 Men, 12 Women, and 18 Children Complete a Task
Work Rate Problem: Calculating Time for 5 Men and 4 Women to Complete a Task