Math Problem Statement
A and B together can do a piece of work in 40 days. A, after working for 24 days, B completes the remaining work alone in 54 days. In how many days B alone can complete the whole work?
Solution
Let's solve this problem step by step.
-
Let the total work be denoted as .
-
The rate of work done by A and B together is of the total work per day. This is because they can complete the whole work in 40 days.
Therefore, A and B together complete of the work per day.
-
Let the rate of work done by A alone be of the work per day, and the rate of work done by B alone be of the work per day.
From the first condition:
- A works for 24 days. During this time, A and B together would have completed of the total work.
So, after 24 days, of the work remains.
- According to the second condition, B alone completes the remaining of the work in 54 days.
Thus, the rate at which B works is of the work per day.
- Now, we know that B completes of the work in one day. Therefore, B alone can complete the entire work in 135 days.
Thus, B alone can complete the whole work in 135 days.
Let me know if you'd like further details or clarifications!
Related Questions:
- If A worked alone, how many days would it take for A to complete the work?
- If A and B work together for 20 days and then B works alone, how many more days would B need to finish the work?
- If A worked for 30 days and B worked for 40 days, what fraction of the work would be completed?
- If A can finish the work in 60 days, how many days will it take for A and B together to finish the work?
- How much more efficient is B compared to A based on their individual working days?
Tip:
In such work-rate problems, converting everything into rates of work per day and then using fractions is the most straightforward approach!
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time Problems
Rates of Work
Fractions
Formulas
Rate of Work = Work / Time
Combined Work Rate: 1 / Total Time = Rate of A + Rate of B
Remaining Work = Total Work - Work Done
Theorems
Work Rate Theorem
Suitable Grade Level
Grades 8-10
Related Recommendation
Solve Work and Time Problem: A and B Completing a Task Together and Separately
Work Rate Problem: A and B Together in 4 Days vs A Alone in 12 Days
Work Rate Problem: A is 4 Times Faster Than B
Work and Time Problem: A and B Completing a Task Together
Find the Value of x in a Work and Time Problem Involving Two Workers