Math Problem Statement

A, B,C started working on a project , but A left the work 9 days before the completion,and B left the work 7 days before the completion , if had A worked for 1 more day the total work would have been completed 2 days before actual time, if B would have worked for 2 more days , the total work would have been completed 3 days before the actual time, In how many days A,B,C can together finish a work if C can alone complete the work in 18 days?

Solution

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Work and Time
Algebra
System of Equations

Formulas

Work done = Rate × Time
(T-9)r_A + (T-7)r_B + T r_C = 1
(T-8)r_A + (T-7)r_B + (T-2)r_C = 1
(T-9)r_A + (T-5)r_B + (T-3)r_C = 1
Total Rate = r_A + r_B + r_C

Theorems

Equation Solving
Algebraic Manipulation

Suitable Grade Level

Grades 10-12