Math Problem Statement
A, B,C started working on a project , but A left the work 9 days before the completion,and B left the work 7 days before the completion , if had A worked for 1 more day the total work would have been completed 2 days before actual time, if B would have worked for 2 more days , the total work would have been completed 3 days before the actual time, In how many days A,B,C can together finish a work if C can alone complete the work in 18 days?
Solution
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time
Algebra
System of Equations
Formulas
Work done = Rate × Time
(T-9)r_A + (T-7)r_B + T r_C = 1
(T-8)r_A + (T-7)r_B + (T-2)r_C = 1
(T-9)r_A + (T-5)r_B + (T-3)r_C = 1
Total Rate = r_A + r_B + r_C
Theorems
Equation Solving
Algebraic Manipulation
Suitable Grade Level
Grades 10-12
Related Recommendation
Solving Work Rate Problem: A, B, and C Work Together
Work and Time Problem: Finding How Long A and C Will Take to Complete a Task
Solve Work Rate Problem: A, B, and C Working Together
Work and Time Problem: A, B, and C's Combined Work Rates and Earnings
Solve Work Rate Problem with A and B Working Together