pekerja 24, menyelesaikan proyek selama 30 hari. pada hari ke-10 tersisa 16 pekerja. berapa hari pekerjaan dapat diselesaikan
Solution
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work rate
Proportion
Linear equations
Formulas
Total work = Number of workers × Time
Remaining work = Total work - Work done
Remaining days = Remaining work / Workers
Theorems
Work-rate theorem
Proportionality in work problems