Math Problem Statement
A, B and C can finish a task in 42 days, 84 days and 28 days, respectively. A started the work. B joined him after 3 days. If C Joined them after 5 days from the beginning, then for many days did A work till the completion of the task?
Solution
Let's break down the problem and solve it step by step.
Step 1: Determine the rate of work for A, B, and C.
- A can finish the task in 42 days, so A's rate of work is of the task per day.
- B can finish the task in 84 days, so B's rate of work is of the task per day.
- C can finish the task in 28 days, so C's rate of work is of the task per day.
Step 2: Analyze the work phases.
-
First 3 days: Only A is working. In 3 days, A completes:
-
From day 4 to day 5 (2 days): A and B are working together. Their combined rate of work is: In 2 days, they complete:
-
From day 6 onward: A, B, and C are all working together. Their combined rate of work is: To add these fractions, we need a common denominator, which is 168: Their combined rate is: So, when A, B, and C work together, they complete of the task per day.
Step 3: Calculate the total work done.
-
In the first 3 days, A completed of the task.
-
In the next 2 days, A and B completed another of the task.
-
The total completed after 5 days is of the task.
-
The remaining work after 5 days is .
Since A, B, and C together complete of the task per day, it will take: for them to complete the remaining work.
Step 4: Calculate how many days A worked.
- A worked alone for 3 days.
- A worked with B for 2 days.
- A worked with B and C for the remaining 12 days.
Thus, A worked a total of:
Final Answer:
A worked for 17 days until the completion of the task.
Would you like any further details or clarifications?
Here are 5 related questions to practice:
- If B started working after 4 days instead of 3, how would it affect the total days A worked?
- What if C joined after 6 days instead of 5? How many days would A have worked?
- If A could finish the task in 35 days instead of 42, how many days would A have worked?
- How would the solution change if B could complete the work in 60 days instead of 84 days?
- What if A, B, and C all started together from day 1? How many days would the task take?
Tip: Breaking down a problem into phases and analyzing each phase separately is a powerful strategy in solving time and work problems.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time
Rate of Work
Fractions
Formulas
Rate of work = 1 / time to complete the task
Total work done = Sum of individual work rates
Theorems
-
Suitable Grade Level
Grades 6-8
Related Recommendation
Work and Time Problem: A, B, and C Completing a Task Together
Work and Time Problem: Finding How Long A and C Will Take to Complete a Task
Work Problem: B and C start, then A finishes the remaining work
Work and Time Problem: A, B, and C Working Together
Solve Work and Time Problem: A, B, and C's Work Completion Time