Math Problem Statement
Solución del problema
Solution
Let's analyze the problem in the image.
Problem:
- We can complete a job in 30 days with p machines.
- With (p + 4) machines, a job with double the difficulty takes 40 days.
- The question asks: How long will it take for (p + 2) machines to complete a job of the same difficulty as the original?
Step-by-Step Solution:
-
Work Rate of p Machines: If p machines can complete a job in 30 days, the total work can be defined as: Thus, the work rate of p machines is:
-
Work Rate of (p + 4) Machines: With (p + 4) machines, the job is twice as difficult and takes 40 days. This means that the amount of work is doubled. The total work is now: The rate of (p + 4) machines can be expressed as:
-
Solving for p: We now solve the equation: Cross-multiplying: Simplifying:
-
Time for (p + 2) Machines: Now that we know p = 2.4, we calculate how long it will take for (p + 2) machines to complete the original job. With (p + 2) = 4.4 machines, the rate is: This rate should equal the rate for the original job: Solving for T:
Thus, the correct answer is 55 days, but it seems the problem might not have been correctly translated into the options provided. Let's reconsider any details or adjustments if needed.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Rate of work
Linear equations
Formulas
Rate = Work / Time
Theorems
-
Suitable Grade Level
High school and above