Math Problem Statement

What is the net present value of Project X, a 3-year project being evaluated by Silver Mountain Fashion? The project would involve an initial investment in equipment of $328,000. To finance the project, Silver Mountain Fashion would borrow $328,000. The firm would receive $328,000 today and pay $417,000 in 3 years (consisting of an interest payment of $89,000 and a principal payment of $328,000). Capital spending would be $0 in year 1 and $0 in year 2. The equipment would be sold for an after-tax cash flow of $52,000 in year 3. Operating cash flows are expected to be 171,000 dollars in year 1, -24,000 dollars in year 2, and 174,000 dollars in year 3. The changes in net working capital are expected to be 14,000 dollars at time 0, -3,000 dollars in year 1, -7,000 dollars in year 2, and -4,000 dollars in year 3. The cost of capital for the project is 9.45 percent and the interest rate on the loan would be 8.33 percent

Solution

To calculate the Net Present Value (NPV) of Project X, we'll follow these steps:


1. Definitions and Components

  • Initial Investment: $328,000
  • Operating Cash Flows (OCF):
    • Year 1: $171,000
    • Year 2: -$24,000
    • Year 3: $174,000
  • Net Working Capital (NWC):
    • Year 0: $14,000
    • Year 1: -$3,000
    • Year 2: -$7,000
    • Year 3: -$4,000
  • Equipment Sale (Year 3): $52,000
  • Loan Payments:
    • Interest in Year 3: $89,000
    • Principal in Year 3: $328,000
  • Cost of Capital: 9.45%

2. Timeline of Cash Flows

We calculate cash flows for each year as follows:

Year 0:

  • Net investment = $328,000 - $14,000 (NWC) = $314,000 outflow

Year 1:

  • OCF = $171,000
  • Change in NWC = -$3,000 (cash inflow)
  • Total cash flow = $171,000 + $3,000 = $174,000 inflow

Year 2:

  • OCF = -$24,000
  • Change in NWC = -$7,000 (cash inflow)
  • Total cash flow = -$24,000 + $7,000 = -$17,000 outflow

Year 3:

  • OCF = $174,000
  • Equipment Sale = $52,000
  • Change in NWC = -$4,000 (cash inflow)
  • Loan Repayment = $417,000 (outflow)
  • Total cash flow = $174,000 + $52,000 + $4,000 - $417,000 = -$187,000 outflow

3. Present Value Calculation

Using the cost of capital (9.45%) as the discount rate, we calculate the present value (PV) of each cash flow:

  • PV Formula:
    PV=Cash Flow(1+r)tPV = \frac{\text{Cash Flow}}{(1 + r)^t}

PVs of Each Year:

  • Year 0: $-314,000 \cdot (1) = -314,000$
  • Year 1: 174,000(1+0.0945)1=158,990\frac{174,000}{(1 + 0.0945)^1} = 158,990
  • Year 2: 17,000(1+0.0945)2=14,214\frac{-17,000}{(1 + 0.0945)^2} = -14,214
  • Year 3: 187,000(1+0.0945)3=143,835\frac{-187,000}{(1 + 0.0945)^3} = -143,835

4. Net Present Value (NPV)

NPV=Sum of PVs for all yearsNPV = \text{Sum of PVs for all years}

NPV=314,000+158,99014,214143,835=312,059NPV = -314,000 + 158,990 - 14,214 - 143,835 = -312,059


Final Answer

The Net Present Value (NPV) of Project X is -$312,059. This means the project is not financially viable under these assumptions.


Would you like a detailed breakdown of any particular step or an explanation of why the project isn't viable?


Relative Questions

  1. How does the cost of capital influence the viability of a project?
  2. What alternative financing methods could improve the project’s NPV?
  3. How are changes in net working capital included in cash flow calculations?
  4. Why is equipment sale added in Year 3's cash flow?
  5. What would happen if operating cash flows were higher in Year 2?

Tip

Always compare NPV results with alternative projects or investments to ensure you're choosing the most profitable option.

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Net Present Value (NPV)
Time Value of Money
Discounting Cash Flows

Formulas

NPV = Σ (Cash Flow_t / (1 + r)^t)
Present Value (PV) = Cash Flow / (1 + r)^t

Theorems

Time Value of Money

Suitable Grade Level

Undergraduate Finance or Business Studies