Math Problem Statement
Solution
The problem states:
- A and B together can complete a task in 35 days.
- If A works alone and completes of the task and then leaves, B will take an additional 90 days to finish the remaining task.
We need to find out how long A would take to complete the entire task alone.
Solution
-
Determine the combined work rate of A and B: Since A and B together can complete the work in 35 days, their combined work rate is:
-
Calculate the amount of work done by A: A completes of the work before leaving, so the remaining work is:
-
Determine B's work rate: B completes of the work in 90 days. Therefore, B's work rate is:
-
Calculate A's work rate: Using the combined rate of A and B, we have: Solving for the work rate of A: Converting to a common denominator:
-
Calculate the time for A to complete the entire task alone: To complete the entire work alone, the time required by A is:
Therefore, the correct answer is approximately 39 days.
Would you like a more detailed breakdown or have questions about specific steps?
Related Questions
- How would the solution change if A and B took 40 days to complete the task together?
- If B could complete the entire task in 100 days alone, how would that affect A’s time?
- What if A completed of the work instead of ?
- How does the work rate concept apply to other collaborative work problems?
- How would a change in the fraction of work A completes alone impact the overall time?
Tip
When tackling work and time problems, break down each part of the task using work rates to simplify complex scenarios.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time
Fractional Work Distribution
Combined Work Rate
Formulas
Work rate formula: 1 / time = work rate
Combined work rate of A and B
Remaining work calculation after partial completion
Theorems
Work and Rate Theorem
Suitable Grade Level
Grades 8-10
Related Recommendation
Work and Time Problem: A and B Completing a Task Together
Solve Work and Time Problem: A and B Completing a Task Together and Separately
Work and Time Problem: Calculating B's Time to Complete Work Alone
Calculating Combined Work Rates: A and B Completing a Job Together
Work Problem: B and C start, then A finishes the remaining work