Math Problem Statement

A और B मिलकर एक कार्य को 35 दिनों में पूरा कर सकते हैं। यदि A अकेले कार्य का 5/7 भाग पूरा करता है और फिर शेष कार्य B को स्वयं पूरा करने के लिए छोड़ देता है, तो कार्य को पूरा करने में कुल 90 दिन लगेंगे। दोनों में से अधिक कुशल A को सारा काम अकेले पूरा करने में कितने दिन लगेंगे?

Solution

The problem states:

  1. A and B together can complete a task in 35 days.
  2. If A works alone and completes 57\frac{5}{7} of the task and then leaves, B will take an additional 90 days to finish the remaining task.

We need to find out how long A would take to complete the entire task alone.

Solution

  1. Determine the combined work rate of A and B: Since A and B together can complete the work in 35 days, their combined work rate is: Work rate of (A + B)=135 work per day\text{Work rate of (A + B)} = \frac{1}{35} \text{ work per day}

  2. Calculate the amount of work done by A: A completes 57\frac{5}{7} of the work before leaving, so the remaining work is: 157=271 - \frac{5}{7} = \frac{2}{7}

  3. Determine B's work rate: B completes 27\frac{2}{7} of the work in 90 days. Therefore, B's work rate is: Work rate of B=27÷90=2630=1315 work per day\text{Work rate of B} = \frac{2}{7} \div 90 = \frac{2}{630} = \frac{1}{315} \text{ work per day}

  4. Calculate A's work rate: Using the combined rate of A and B, we have: 135=Work rate of A+1315\frac{1}{35} = \text{Work rate of A} + \frac{1}{315} Solving for the work rate of A: Work rate of A=1351315\text{Work rate of A} = \frac{1}{35} - \frac{1}{315} Converting to a common denominator: =91315=8315 work per day= \frac{9 - 1}{315} = \frac{8}{315} \text{ work per day}

  5. Calculate the time for A to complete the entire task alone: To complete the entire work alone, the time required by A is: Time for A=18315=3158=39.37539.4 days\text{Time for A} = \frac{1}{\frac{8}{315}} = \frac{315}{8} = 39.375 \approx 39.4 \text{ days}

Therefore, the correct answer is approximately 39 days.

Would you like a more detailed breakdown or have questions about specific steps?


Related Questions

  1. How would the solution change if A and B took 40 days to complete the task together?
  2. If B could complete the entire task in 100 days alone, how would that affect A’s time?
  3. What if A completed 35\frac{3}{5} of the work instead of 57\frac{5}{7}?
  4. How does the work rate concept apply to other collaborative work problems?
  5. How would a change in the fraction of work A completes alone impact the overall time?

Tip

When tackling work and time problems, break down each part of the task using work rates to simplify complex scenarios.

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Work and Time
Fractional Work Distribution
Combined Work Rate

Formulas

Work rate formula: 1 / time = work rate
Combined work rate of A and B
Remaining work calculation after partial completion

Theorems

Work and Rate Theorem

Suitable Grade Level

Grades 8-10