Math Problem Statement
If 20% of a certain quantity of work is done by A and after that the remaining 80% of the work is done by B, the work will be completed in 20 days. If 80% of the work is done by A and after that the remaining 20% of the work is done by B, the work will be completed in 30 days. If A & B work together how many days are required to complete the work?
Solution
Let the total amount of work be 1 unit.
Case 1: 20% of the work is done by A, and 80% is done by B
- Work done by A:
- Work done by B:
- Total time to complete the work: 20 days.
Let 's rate of work be units/day and 's rate of work be units/day.
From this, the total time can be expressed as:
Case 2: 80% of the work is done by A, and 20% is done by B
- Work done by A:
- Work done by B:
- Total time to complete the work: 30 days.
From this, the total time can be expressed as:
Solving the system of equations
We now have two equations:
Let's solve these equations to find and .
Multiply equation (1) by 4 and equation (2) by 1 to simplify:
Now subtract equation (2) from equation (3):
Now, substitute into equation (1):
Working Together
When A and B work together, their combined rate is:
Let’s calculate the combined rate and the total number of days required to finish 1 unit of work:
Solving this, we get:
Thus, if A and B work together, they will complete the work in approximately 11.11 days.
Would you like any further clarification or details?
Here are 5 questions to consider:
- What is the significance of the rates and in this problem?
- How would the solution change if A and B had different individual rates?
- Can you derive the solution without solving the system of equations directly?
- What happens if A and B start working together halfway through the project?
- How does the combined work rate impact overall efficiency?
Tip: When solving work-rate problems, it's often helpful to represent rates as fractions of the total work and use algebraic methods for more complex situations.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time
Rates of Work
System of Equations
Formulas
Total work = 1 unit
Rate of A = a units/day
Rate of B = b units/day
System of equations for work completion: (Work done by A / Rate of A) + (Work done by B / Rate of B) = Total time
Theorems
Work Rate Theorem (Work = Rate × Time)
Suitable Grade Level
Grades 9-12