Math Problem Statement

if a 15 men complete a work by 6 days due to some reason five man left the work then how many days the remaining work will complete

Solution

To solve this problem, we can apply the concept of work done and man-days.

Step 1: Determine total man-days for the initial work.

If 15 men complete the work in 6 days, the total man-days of work can be calculated as: Total man-days=15men×6days=90man-days.\text{Total man-days} = 15 \, \text{men} \times 6 \, \text{days} = 90 \, \text{man-days}. This means the entire work requires 90 man-days to be completed.

Step 2: Calculate work done before the 5 men leave.

If 15 men are working for some time before 5 leave, we need to know how much work they have done in the days they've worked so far.

Let’s assume the work continues for xx days before 5 men leave.

The work done in xx days with 15 men is: Work done=15men×xdays=15xman-days.\text{Work done} = 15 \, \text{men} \times x \, \text{days} = 15x \, \text{man-days}.

Step 3: Set up the remaining work.

After 5 men leave, there are only 10 men left to continue the work. The remaining work will be: Remaining work=90man-days15xman-days.\text{Remaining work} = 90 \, \text{man-days} - 15x \, \text{man-days}. Now, the remaining work needs to be completed by 10 men, so the number of days required for them to finish the remaining work is: Remaining days=Remaining work10.\text{Remaining days} = \frac{\text{Remaining work}}{10}.

Step 4: Calculate the time it takes to finish the remaining work.

Let’s assume that after 5 men leave, the remaining work will be completed in yy days. Therefore, we have: 15x+10y=90.15x + 10y = 90. We need more information about how long the 15 men worked before 5 left (i.e., xx) to proceed. Could you tell me how many days the 15 men worked before the 5 men left?

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Work and Time
Man-Days
Algebra

Formulas

Total man-days = men × days
Remaining work = Total man-days - Work done
Remaining days = Remaining work / men

Theorems

Work and Time Theorem

Suitable Grade Level

Grades 6-8