Math Problem Statement
Please solve the attached problem
Solution
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Probability Theory
Gaussian Distribution
Critical Path Method
Formulas
Z = (X - μ) / σ
Path Time = Sum of Activity Means
Standard Deviation of Path Time = sqrt(Sum of Squared Deviations)
Theorems
Central Limit Theorem
Suitable Grade Level
Undergraduate level (Construction Management, Probability and Statistics)
Related Recommendation
Project Management: Calculating Probability of Completion in Less Than 28 Weeks
Project Completion Time and Probabilities in Project Management
Solving Critical Path Problems: Earliest Start Time and Float Time Calculation
Calculate Expected Time and Variance for Project Activities using PERT
Project Management: Calculating Expected Completion Time and Probability