Maximize (Profit) Z=80x1 + 120x2 Subject to the constraints: i. Production Capacity Constraint: x1+x2<=9 ii. Supply Constraint: x1>=2, x2>=3 iii. Machine-hour Constraint: 20x1+50x2<=360 It is required to determine the Production Schedule for Maximum Profit and calculate the profit using Graphical Method.

Solution

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Linear Programming
Graphical Method
Optimization

Formulas

Objective Function: Z = 80x1 + 120x2
Production Capacity Constraint: x1 + x2 <= 9
Supply Constraint: x1 >= 2, x2 >= 3
Machine-hour Constraint: 20x1 + 50x2 <= 360