Math Problem Statement

so im doing general maths yeah. so lets say an activity G is reduced by 3 but G's est and lst is different, so the float time is not 0. therefore this activity is not on the critical path. so if g's delayed by lets say 3 days, will this cause there to be an effect on the critical path? like im confused one side im thinking no effect since G is not even on the critical path, so the min time for the critcal path stays the same. but otherwise, this delay in G may cause a delay in another activity like J, which is on the cirtical path, so there may be an effect on the critical path right? which side is correct?

Solution

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Critical Path Method (CPM)
Project Management
Float Time

Formulas

Float = Latest Start Time - Earliest Start Time
Critical Path = Longest Duration Path

Theorems

Critical Path Theorem