An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated times: Activity Immediate Time Predecessors (days) A Prepare preliminary sketches B Outline specifications 2 1 C Prepare drawings A 3 D Write specifications A, B 2 E Run off prints C, D 1 F Have specification B, D 3 G Assemble bid packages E, F 1

Solution

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Project Scheduling
Critical Path Method
Network Diagrams

Formulas

Earliest Start (ES) = Max(EF of predecessor activities)
Earliest Finish (EF) = ES + Duration
Latest Finish (LF) = Min(LS of successor activities)
Latest Start (LS) = LF - Duration