firstly i have some corrections for you: the original project duration i found was only 23 days. i did this by finding the est and lst of each activity. and i found three critical paths as follows: ABCFHIJ, ABDHIJ, ABEIJ. not sure if all of them are right. so with a 3 day delay, the project would've been extended to 24 days. now do the question i asked