Math Problem Statement
Lambda Computer Products competed for and won a contract to produce two prototype units of a new type of computer that is based on laser optics rather than on electronic binary bits.
The first unit produced by Lambda took 5,000 hours to produce and required $250,000 worth of material, equipment usage, and supplies. The second unit took 3,750 hours and used $212,500 worth of materials, equipment usage, and supplies. Labor is $25 per hour. The company expects “learning” to occur relative to labor and also the pricing of parts from suppliers. Use Exhibit 6.5.
Lambda was asked to present a bid for 10 additional units as soon as the second unit was completed. Production would start immediately. What would this bid be?
Solution
To calculate the bid for 10 additional units based on the given information, we need to consider the learning curve effect, particularly for labor, and the cost of materials. Here’s how you can approach this problem:
Step 1: Determine the learning curve percentage
- The first unit took 5,000 hours, and the second unit took 3,750 hours.
- The learning curve can be calculated as the ratio of the time it took to produce the second unit to the time it took to produce the first unit:
This indicates a 75% learning curve.
Step 2: Calculate the total labor hours for 10 additional units
Given the 75% learning curve, the labor hours decrease as more units are produced. For each doubling of production, labor hours should reduce to 75% of the previous total.
Using the cumulative average time formula, the total labor hours for units after producing the first two units can be approximated using:
Where:
- labor hours for the first unit
- cumulative number of units
- log(learning curve)/log(2)
Given:
- hours
- Learning curve = 0.75 →
Step 3: Calculate the labor hours for the 10 additional units
To determine the labor hours for the next 10 units, you would calculate the cumulative hours required for 12 units and subtract the hours for the first 2 units.
- Cumulative hours for 12 units:
- Cumulative hours for the first 2 units:
- Total hours for the next 10 units:
Step 4: Calculate the labor cost
The labor cost for the 10 additional units:
Step 5: Estimate material and other costs
Given that the material cost for the second unit was $212,500 (a 15% reduction from the first unit), and if we assume a similar learning effect:
Assuming this trend continues:
Step 6: Calculate the total bid
Adding the labor cost and material costs together gives:
Therefore, the bid for the 10 additional units would be approximately $2,250,905.
Additional Considerations:
- This calculation assumes the learning curve continues similarly for both labor and material costs.
- If the learning curve flattens or the material costs don’t decrease as expected, the actual bid might need adjustments.
Would you like further details or explanations on any step? Here are some related questions that might help you understand this better:
- How is a learning curve percentage determined in production?
- What factors influence the material cost decrease in production?
- How does labor cost impact overall project bidding?
- What is the importance of accurate cost estimation in competitive bidding?
- How would the bid change if the learning curve was different?
Tip: Always consider potential changes in the learning curve when scaling production to ensure accurate bids and forecasts.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Learning Curve
Exponential Growth/Decay
Cost Estimation
Cumulative Average Time Formula
Formulas
Learning Curve (LC) = Time for 2nd Unit / Time for 1st Unit
T_n = T_1 * n^b
Labor Cost = Total Labor Hours * Labor Rate
Material Cost Estimation = Previous Material Cost * Reduction Factor
Theorems
Learning Curve Theorem
Exponential Decay in Labor Costs
Suitable Grade Level
College/Professional Level
Related Recommendation
Estimating Manufacturing Labor Costs Using Learning Curve and Constant Rate Methods
Learning Curve Cost Estimation for Cruise Missile Guidance Control Production
Estimating Labor Hours Using Learning Curves: Example and Solution
Understanding Labor Hour Calculation Using Learning Curve and Cumulative Improvement Factor
Learning Curve Equation: Solving for k and Days for Production Target