Math Problem Statement
if a does 33 by 1/3 % of the work in 17 days then in how many days whole work will be completed
Solution
To solve this problem, we need to determine how long it would take for to complete the entire work based on the given information.
Step 1: Determine the fraction of work done by .
- completes of the work in 17 days.
- can be written as .
This means does of the total work in 17 days.
Step 2: Determine the work rate of .
- Work rate is given by work done per day.
- .
Step 3: Calculate the time required to complete the whole work.
- To complete the whole work, would need days, where:
So, would take 5100 days to complete the whole work.
Would you like any further details or explanations?
Here are 8 related questions for practice:
- If does 25% of the work in 20 days, how long will take to complete the whole work?
- What is the work rate of a person who completes 10% of a task in 5 days?
- If can complete the entire work in 30 days, how much work does complete in 10 days?
- Two people can complete a task together in 15 days. If one person works twice as fast as the other, how long would each take to complete the work alone?
- If a task is 60% complete and 12 days have passed, how long will it take to finish the remaining work at the same rate?
- How would the time change if worked 10% faster on the same task?
- If the work rate doubles, how many days will it take to complete a task that originally took 20 days?
- What fraction of the work is done after 25 days if a person completes the work in 100 days?
Tip: When dealing with work problems, it’s often useful to express rates as fractions of the whole task and to set up equations that relate these rates to time.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Percentage
Work and Time Problems
Formulas
Work rate formula: R = \frac{\text{Work done}}{\text{Time taken}}
Theorems
-
Suitable Grade Level
Grades 7-9
Related Recommendation
Calculate Time to Complete a Project with Different Work Rates
Calculate Efficiency and Work Rates: A and B Problem Solution
Calculate Completion Time for Work with A, B, and C
Calculate Work Completion Time with A and B Working Together
Find the Value of x in a Work and Time Problem Involving Two Workers