Math Problem Statement

Dinding tembok tepi jalan akan di cat oleh 42 orang pekerja dengan target pekerjaan selesai dalam waktu 36 hari. Pada hari ke-7 pekerjaan dihentikan karena hujan selama total 3 hari. Kemudian, pada hari ke-20 pekerjaan dihentikan lagi selama 2 hari karena kehabisan materi. Jika pekerjaan itu harus selesai sesuai target awal, maka jumlah pekerja yang harus ditambahkan adalah ...

Solution

The question in the image provides the following scenario:

  • 42 workers are painting a wall with a target to complete the job in 36 days.
  • On the 7th day, work stopped due to rain for a total of 3 days.
  • On the 20th day, work stopped again for 2 days because they ran out of materials.
  • Despite the delays, the job must be completed within the original 36-day deadline.
  • The question asks how many additional workers are needed to meet the original deadline.

Step-by-step Solution:

  1. Initial Work Rate:

    • The total number of worker-days required to complete the job is 42 workers×36 days=1512 worker-days42 \text{ workers} \times 36 \text{ days} = 1512 \text{ worker-days}.
  2. Work Halted:

    • On the 7th day, the work stopped for 3 days due to rain. So, no work was done on days 7, 8, and 9. They resumed work on day 10.
    • On the 20th day, work stopped again for 2 days due to a lack of materials. So, no work was done on days 20 and 21. Work resumed on day 22.

    Therefore, a total of 3+2=53 + 2 = 5 days were lost due to these interruptions.

  3. Remaining Work Time:

    • Since the total target was to finish in 36 days, the workers now only have 365=3136 - 5 = 31 working days to finish the job.
  4. Work Rate Adjustment:

    • The job requires 1512 worker-days in total, and after the delays, only 31 days remain.
    • Let xx be the new required number of workers. The equation is: x×31=1512x \times 31 = 1512 Solving for xx: x=15123148.77x = \frac{1512}{31} \approx 48.77 Since the number of workers must be a whole number, we round xx up to 49 workers.
  5. Additional Workers Needed:

    • Initially, there were 42 workers. Now, we need 49 workers, so the number of additional workers required is: 4942=7 additional workers49 - 42 = 7 \text{ additional workers}

Answer:

The number of additional workers needed is 7.


Would you like more details or have any questions about the solution?

Here are 5 related questions to further your understanding:

  1. What happens if only 6 additional workers are added instead of 7?
  2. How would the answer change if there was only a 4-day delay instead of 5 days?
  3. How can you calculate the daily productivity rate of each worker?
  4. What if the target was extended by 5 days due to delays?
  5. How would the solution differ if fewer than 42 workers started the project?

Tip: When calculating worker-days, always break down the total work required before adjusting for interruptions.

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Work and Time Problems
Algebra

Formulas

Total work = Number of workers × Number of days
New workers required = Total work / Remaining days
Additional workers = New workers - Initial workers