Math Problem Statement
Dinding tembok tepi jalan akan di cat oleh 42 orang pekerja dengan target pekerjaan selesai dalam waktu 36 hari. Pada hari ke-7 pekerjaan dihentikan karena hujan selama total 3 hari. Kemudian, pada hari ke-20 pekerjaan dihentikan lagi selama 2 hari karena kehabisan materi. Jika pekerjaan itu harus selesai sesuai target awal, maka jumlah pekerja yang harus ditambahkan adalah ...
Solution
The question in the image provides the following scenario:
- 42 workers are painting a wall with a target to complete the job in 36 days.
- On the 7th day, work stopped due to rain for a total of 3 days.
- On the 20th day, work stopped again for 2 days because they ran out of materials.
- Despite the delays, the job must be completed within the original 36-day deadline.
- The question asks how many additional workers are needed to meet the original deadline.
Step-by-step Solution:
-
Initial Work Rate:
- The total number of worker-days required to complete the job is .
-
Work Halted:
- On the 7th day, the work stopped for 3 days due to rain. So, no work was done on days 7, 8, and 9. They resumed work on day 10.
- On the 20th day, work stopped again for 2 days due to a lack of materials. So, no work was done on days 20 and 21. Work resumed on day 22.
Therefore, a total of days were lost due to these interruptions.
-
Remaining Work Time:
- Since the total target was to finish in 36 days, the workers now only have working days to finish the job.
-
Work Rate Adjustment:
- The job requires 1512 worker-days in total, and after the delays, only 31 days remain.
- Let be the new required number of workers. The equation is: Solving for : Since the number of workers must be a whole number, we round up to 49 workers.
-
Additional Workers Needed:
- Initially, there were 42 workers. Now, we need 49 workers, so the number of additional workers required is:
Answer:
The number of additional workers needed is 7.
Would you like more details or have any questions about the solution?
Here are 5 related questions to further your understanding:
- What happens if only 6 additional workers are added instead of 7?
- How would the answer change if there was only a 4-day delay instead of 5 days?
- How can you calculate the daily productivity rate of each worker?
- What if the target was extended by 5 days due to delays?
- How would the solution differ if fewer than 42 workers started the project?
Tip: When calculating worker-days, always break down the total work required before adjusting for interruptions.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time Problems
Algebra
Formulas
Total work = Number of workers × Number of days
New workers required = Total work / Remaining days
Additional workers = New workers - Initial workers
Theorems
Work Formula
Suitable Grade Level
Grades 8-10