Math Problem Statement
Jika 15 pekerja dapat mengaspal jalan sepanjang 18 km dalam waktu 40 hari. Berapa hari yang dibutuhkan oleh 40 pekerja untuk mengaspal jalan sepanjang 22 km?
Solution
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time
Proportional Reasoning
Inverse Proportion
Formulas
Work Total = Number of Workers × Road Length × Time
t = Total Work / (Number of Workers × Road Length)
Theorems
Proportionality Theorem (Work and Time)
Suitable Grade Level
Grades 9-12