Math Problem Statement
Apples are processed through a two-step process. First, the fruit is cleaned in a machine with a capacity of 1,500 apples per hour. Next, the fruit is labelled with a machine that has a capacity of 500 apples per hour. Demand for apples exceeds supply.
In a pull system, what will be the utilization of the first machine?
Note: Round your answer to 3 decimal places.
Solution
In a pull system, the utilization of a machine is determined by the demand rate, and since the demand for apples exceeds supply, the pull system would operate based on the capacity of the machine with the lowest throughput.
Here, the capacities are:
- Cleaning machine capacity = 1,500 apples per hour
- Labeling machine capacity = 500 apples per hour
In a pull system, the bottleneck will be the labeling machine, because it has the lowest capacity (500 apples per hour).
To find the utilization of the cleaning machine, we need to determine how much of its capacity is being used, which is driven by the labeling machine's capacity (since the cleaning machine has a higher capacity but will be synchronized to match the labeling machine's throughput).
Utilization Formula:
Now, substitute the given values:
Thus, the utilization of the cleaning machine is 0.333, or 33.3% when rounded to three decimal places.
Let me know if you have any further questions or need clarification!
Further questions to explore:
- What is the utilization of the labeling machine in this system?
- How would the system be affected if the labeling machine capacity increased to 1,000 apples per hour?
- What would happen to the system's overall throughput if the cleaning machine capacity decreased to 1,200 apples per hour?
- How does the concept of a bottleneck apply in manufacturing systems, and why is it important?
- What is the relationship between machine utilization and system efficiency in a pull system?
Tip: Always identify the bottleneck in a pull system, as it dictates the pace of the entire process.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Utilization
Systems Analysis
Bottleneck Analysis
Formulas
Utilization of cleaning machine = Capacity of labeling machine / Capacity of cleaning machine
Theorems
Bottleneck Theory
Pull System Analysis
Suitable Grade Level
Grades 11-12
Related Recommendation
Utilization of Washers in a Laundry Business - Step-by-Step Calculation
Implied Utilization Calculation for Resource with Two Client Types
Calculate Process Utilization for Batch Production
Calculate the Utilization Rate for Amy Xia's Hammer Production Plant
Flow Rate and Capacity of Bank Tellers with Utilization and Processing Time