Math Problem Statement
A process requires a 14 minute setup for each batch. When producing, the process can produce one unit every 16 minutes. Demand for the product is 3 units per hour.
With a batch size of 12 units, what is the process utilization?
Solution
To calculate the process utilization, we need to determine how much of the available time the process is being used to meet demand. Here are the steps:
Step 1: Determine total production time for one batch
The process requires a 14-minute setup time for each batch and can produce one unit every 16 minutes. With a batch size of 12 units, the total production time for a batch is:
So, the total time to complete one batch, including setup, is:
Step 2: Determine how many batches are required to meet demand
The demand is 3 units per hour, which equals:
Now, divide the total demand by the batch size to determine how many batches are required:
Step 3: Calculate total time spent producing batches
Each batch takes 206 minutes to complete. For 6 batches, the total time spent producing during the day is:
Step 4: Determine available time
There are 24 hours in a day, or:
Step 5: Calculate utilization
The process utilization is the ratio of the time spent producing to the total available time:
Final Answer:
The process utilization is 85.83%.
Would you like further details or have any questions?
Related Questions:
- How does changing the batch size affect process utilization?
- What happens to utilization if the demand increases to 4 units per hour?
- How would reducing the setup time to 10 minutes impact utilization?
- What is the impact on utilization if the production time per unit drops to 12 minutes?
- How does the utilization change if the process runs only for 16 hours per day?
Tip:
Batch size directly affects the balance between setup time and production time, so optimizing batch sizes can improve overall process efficiency.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Process Utilization
Time Management
Batch Production
Formulas
Production time for a batch = batch size × time per unit
Total time per batch = setup time + production time
Number of batches required = total demand / batch size
Utilization = total production time / available time
Theorems
Ratio theorem for utilization calculation
Suitable Grade Level
Grades 9-12
Related Recommendation
Average Labor Utilization in a Two-Resource Manufacturing Process
Implied Utilization Calculation for Resource with Two Client Types
Calculate the Utilization Rate for Amy Xia's Hammer Production Plant
Optimal Processing Time for 11 Tasks on 5 Processors in 24 Hours
Utilization of Washers in a Laundry Business - Step-by-Step Calculation