A process requires a 14 minute setup for each batch. When producing, the process can produce one unit every 16 minutes. Demand for the product is 3 units per hour.

With a batch size of 12 units, what is the process utilization?

Solution

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Process Utilization
Time Management
Batch Production

Formulas

Production time for a batch = batch size × time per unit
Total time per batch = setup time + production time
Number of batches required = total demand / batch size
Utilization = total production time / available time