Math Problem Statement
A school has 96 students and 59 staff. 20 students require 20 staff at all times while the remaining 76 students need 31 staff at all times. If 8 staff clocked in at 7:15AM and needed their lunch within 5 hours, 16 staff clocked in at 6:45AM, and 15 clocked in at 7:45AM and all need their lunch within 5 hours of when they clocked in, how many additional staff would it take to ensure staff received their 30-minute lunch and maintain current ratios? Show a schedule
Solution
Problem Breakdown:
-
Total students: 96 students.
- 20 students require 20 staff (1-to-1 ratio).
- 76 students require 31 staff (approx. 1 staff for every 2.45 students).
-
Staff required to supervise all students:
- For the 20 students, 20 staff are needed.
- For the 76 students, 31 staff are needed.
- So, total staff required at all times: staff.
-
Staff clock-in times and lunch requirements:
- 8 staff clocked in at 7:15 AM, lunch needed by 12:15 PM (within 5 hours).
- 16 staff clocked in at 6:45 AM, lunch needed by 11:45 AM.
- 15 staff clocked in at 7:45 AM, lunch needed by 12:45 PM.
-
Lunch breaks: All staff need a 30-minute lunch break within 5 hours of clocking in.
Solution:
Step 1: Assess the staff availability during lunch periods
We must ensure 51 staff are always available, even when staff are on their 30-minute lunch break. Let's determine the staff available during the lunch windows and then calculate how many additional staff are needed.
Step 2: Calculate lunch windows
-
Staff clocking in at 6:45 AM:
- Lunch window: 11:45 AM to 12:15 PM.
- 16 staff need lunch during this window.
-
Staff clocking in at 7:15 AM:
- Lunch window: 12:15 PM to 12:45 PM.
- 8 staff need lunch during this window.
-
Staff clocking in at 7:45 AM:
- Lunch window: 12:45 PM to 1:15 PM.
- 15 staff need lunch during this window.
Step 3: Schedule and calculate shortages during lunch windows
We will analyze each 30-minute lunch window and check how many staff are available, then determine if we need additional staff to maintain the required 51 staff on duty.
-
11:45 AM - 12:15 PM (16 staff on lunch):
- Available staff: staff (since 16 are on lunch).
- Staff required: 51.
- Staff shortage: additional staff needed.
-
12:15 PM - 12:45 PM (8 staff on lunch):
- Available staff: staff (since 8 are on lunch).
- Staff required: 51.
- Staff shortage: additional staff needed.
-
12:45 PM - 1:15 PM (15 staff on lunch):
- Available staff: staff (since 15 are on lunch).
- Staff required: 51.
- Staff shortage: additional staff needed.
Step 4: Minimum additional staff needed
The largest shortage occurs during the 11:45 AM - 12:15 PM window, where 28 additional staff are required.
Thus, the school would need to hire 28 additional staff to ensure all staff receive their 30-minute lunch break and the student-to-staff ratios are maintained at all times.
Schedule Summary:
- 11:45 AM - 12:15 PM: 28 additional staff required.
- 12:15 PM - 12:45 PM: 20 additional staff required.
- 12:45 PM - 1:15 PM: 27 additional staff required.
Tip:
Staggering lunch breaks more efficiently, or introducing floating staff who only work during peak times, could reduce the number of additional hires needed.
Follow-up Questions:
- How would reducing the lunch break time impact the staff requirement?
- What if additional staff clocked in at 8:00 AM—how would that affect the schedule?
- Could shifts be adjusted to accommodate lunch without hiring more staff?
- What is the cost implication of hiring 28 additional staff for the school?
- How could technology or automation reduce the staff requirements in such a scenario?
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Ratios
Time Management
Subtraction
Formulas
Total staff required = students needing staff * staff per student ratio
Available staff during lunch = Total staff - Staff on lunch
Theorems
-
Suitable Grade Level
Grades 9-12
Related Recommendation
Calculating Additional Staff Needed for Lunch Coverage in a School Setting
Staff Break Management for 96 Students and 59 Staff: Solving for Additional Staff Needs
Staffing Calculations for a School: Maintaining Ratios During Lunch Breaks
Generating Waitstaff Schedule Using First-Hour Principle
Optimize Staff Composition for Cost Savings Using Linear Programming