Math Problem Statement

This question relates to the Quiz 6.4 diagram, which shows the NPV profile for Project Z.  Project Z is an independent project and the firm as sufficient capital to undertake all projects under consideration.

If the cost of capital is 14.9%, is this project acceptable, and why/why not?

Question 3Answer

a.

It depends on whether the project is better than alternative projects the firm could undertake.

b.

No, because the NPV of the project is negative.

c.

No, because the project is only acceptable if the cost of capital is 10%.

d.

Yes, it is acceptable for all costs of capital greater than 13%.

Solution

Ask a new question for Free

By Image

Drop file here or Click Here to upload

Math Problem Analysis

Mathematical Concepts

Net Present Value (NPV)
Cost of Capital
Internal Rate of Return (IRR)

Formulas

NPV = Σ (Ct / (1 + r)^t) - C0
IRR determination where NPV = 0

Theorems

-

Suitable Grade Level

University - Finance and Economics