Math Problem Statement
Volume is 32,000, TPH target is 65, and Headcount is 179. How much VTO must I offer to achieve a 3.08 shift length? Select the correct answer.
15
21
19
11
Solution
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Basic Arithmetic
Division
Average Rate
Proportions
Formulas
Total required output = Volume ÷ Shift Length
Total people required = Total required output ÷ TPH target
VTO offered = Total headcount - Total people required
Theorems
-
Suitable Grade Level
Grades 6-8