Math Problem Statement
The Table below show the schedule for eight activities in a project.
Activity
Immediate Predecessor
Time
(Weeks)
Early Start Time (Weeks)
Early Finish Time (Weeks)
Latest Start Time (Weeks)
Latest Finish Time (Weeks)
A
6
0
6
3
9
B
5
0
5
0
5
C
A
3
6
9
11
14
D
A
2
6
8
9
11
E
B
4
5
9
10
14
F
B
6
5
11
5
11
G
C, E
5
9
14
14
19
H
D, F
8
11
19
11
19
If the cost to execute activities A, B, C, D, E, F, G, and H for this project are R10200, R6500, R5100, R4200, R8400, R4800, R5200, and R4000 respectively, then:
The total cost of executing the activities in the 11th week of the project, if the project started early is:
Question 6Answer
a. R1840
b. R500
c. R4600
d. R6700
e. None of the above
Solution
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Project Management
Cost Calculation
Scheduling
Formulas
Total cost = Sum of costs of active activities during the specified week
Theorems
Critical Path Method (CPM)
Suitable Grade Level
University/Professional Level (Project Management)
Related Recommendation
Solving Critical Path Problems: Earliest Start Time and Float Time Calculation
Critical Path Analysis: Finding Earliest Start, Float, and Critical Path in Project Networks
Calculate Total Job Cost for Xavier Company Engagement - Tech Solutions
Critical Path Analysis for Project Management - Duration Calculation of Activities E and G
Critical Path Method Analysis with Float Calculation for Project Management