Math Problem Statement
Solution
To solve this problem, we’ll work through the information provided and calculate the total days required to complete the batch of pens.
Step-by-Step Solution:
-
Calculate the daily output of one machine:
- The factory can complete the batch in 20 days using 12 machines.
- So, total machine-days needed = machine-days.
-
Calculate the output rate per day for each machine:
- Each machine contributes to this output, so the work done per machine per day = of the batch.
-
Output from 8 machines for the first 9 days:
- For the first 9 days, only 8 machines were operational.
- The work done in 9 days by 8 machines = machine-days.
-
Remaining work:
- Total work needed is 240 machine-days.
- Work completed in the first 9 days is 72 machine-days.
- Remaining work = machine-days.
-
Calculate additional days with all 12 machines:
- From day 10 onward, all 12 machines are used.
- Days required to complete 168 machine-days of work with 12 machines = days.
-
Total days taken:
- The first phase took 9 days, and the second phase took 14 days.
- Total days = days.
Answer:
The total number of days taken to make the batch of pens is 23 days.
Would you like a detailed explanation on any step, or have any further questions?
Here are five related questions to extend your understanding:
- What would happen to the total time if only 6 machines were operational in the first 9 days?
- How many days would it take if the factory had 15 machines instead of 12?
- What is the effect on the total production time if the factory works an extra 2 hours per day?
- How would the answer change if, instead of day 10, all 12 machines became available on day 8?
- How much work does one machine complete in 5 days at this rate?
Tip: When solving similar problems, try breaking down the work into manageable chunks, as we did here by calculating machine-days. This approach helps simplify complex multi-step calculations.
Ask a new question for Free
By Image
Drop file here or Click Here to upload
Math Problem Analysis
Mathematical Concepts
Work and Time
Rate of Work
Problem-Solving
Formulas
Work = Rate x Time
Total work needed = 20 days x 12 machines = 240 machine-days
Remaining work = Total work - Initial work
Additional days = Remaining work / Machines
Theorems
Work and Time Theorem
Suitable Grade Level
Grades 9-10
Related Recommendation
Calculating Total Days to Complete a Batch of Pens with Machine Downtime
Work Rate Problem: Calculating Days for Batch Production with Machine Fault
Work Schedule Problem: How Many Products Should Be Made Daily?
Factory Production Calculation: How to Find Total Articles Produced in a Day
Time Calculation for Road Construction with Reducing Workforce